Content
 BigPicture

About BigPicture

BigPicture installation and updates

Quick start with BigPicture

BigPicture Sizing Guide

Cloud vs. Server - Key Differences in BigPicture on These Platforms

BigPicture Export

Progress Tracking

Tutorials and tips

Integrations

 BigPicture release notes

BigPicture Cloud Backlog

 BigGantt

About BigGantt

BigGantt - Important Notice

BigGantt installation and updates

BigGantt Cloud Backlog

Cloud vs. Server - Key Differences in BigPicture on These Platforms

 BigGantt release notes

Shortcuts
 Release notes
 BigPicture
 Jira Cloud

 Jira Server

 Trello

 BigGantt
 Jira Cloud

 Jira Server

 BigTemplate
 Jira Cloud

 Jira Server

 BigPicture Enterprise
 Jira Cloud

 Jira Server

Knowledge Base

Tutorials and tips

Search

ASAP mode

Once this checkbox is marked the link will always set:

  • the earliest possible Start Date of the linked target task if Start Date is the target

  • the earliest possible End Date of the linked target task if End Date is the target.

In other words - link in ASAP mode always schedules target task as soon as possible based on dependency type. There are no restrictions on how many links are created for each source or target task as long as they are not creating a circular relationship (discussed here). If a task is moved to a prohibited position (based on link type and mode) it is moved back/forward to the appropriate position.