Content
 BigPicture

About BigPicture

BigPicture installation and updates

Quick start with BigPicture

BigPicture Sizing Guide

Cloud vs. Server - Key Differences in BigPicture on These Platforms

BigPicture Export

Progress Tracking

Tutorials and tips

Integrations

 BigPicture release notes

BigPicture Cloud Backlog

 BigGantt

About BigGantt

BigGantt - Important Notice

BigGantt installation and updates

BigGantt Cloud Backlog

Cloud vs. Server - Key Differences in BigPicture on These Platforms

 BigGantt release notes

Shortcuts
 Release notes
 BigPicture
 Jira Cloud

 Jira Server

 Trello

 BigGantt
 Jira Cloud

 Jira Server

 BigTemplate
 Jira Cloud

 Jira Server

 BigPicture Enterprise
 Jira Cloud

 Jira Server

Knowledge Base

Tutorials and tips

Search

Loops and Cross-Program Relationship

In BigPicture, task links have a direct effect on the Start and End Dates, so some combinations of links will not be allowed. This concerns what we call "loops". Let's imagine the following type of inter-dependency:

Task A (Ends) → (Starts) Task B

Task B (Ends) → (Starts) Task C

Task B (Ends) → (Starts) Task C

Please note that the same effect can be achieved using only 2 tasks.
Such a combination of links on these tasks would result in Task A rescheduling Task B, Task B rescheduling Task C, Task C rescheduling Task A, and so on and so forth. This sort of paradox would create an infinitive number of re-calculation and could possibly crush our environment. This is why our app Power-Up will not allow it and will return a Warning.