Search

Content
 BigPicture

About BigPicture

BigPicture installation and updates

Quick start with BigPicture

BigPicture Sizing Guide

Cloud vs. Server - Key Differences in BigPicture on These Platforms

BigPicture Export

Progress Tracking

Tutorials and tips

Integrations

 BigPicture 7.10 and earlier

Concept of a Program

Setting up BigGantt and BigPicture to support next-gen projects


 BigPicture release notes

BigPicture Cloud Backlog

 BigGantt

About BigGantt

BigGantt installation and updates

Cloud vs. Server - Key Differences in BigPicture on These Platforms

 BigGantt release notes

Shortcuts
 Release notes
 BigPicture
 Jira Cloud

 Jira Server

 Trello

 BigGantt
 Jira Cloud

 Jira Server

 BigTemplate
 Jira Cloud

 Jira Server

 BigPicture Enterprise
 Jira Cloud

 Jira Server

Knowledge Base

Tutorials and tips


Dependency links

The Board 2.0 introduces a new concept of links which are referred to as soft-links and strong links.

The soft-link can be mapped to a Jira dependency link, just like other dependencies in the app in the Link configuration.

Feature

Description

Correct links (healthy dependency)

The healthy dependencies are presented when the successor is planned in the same (orange lines) or future (green lines) timebox (Program Increment or Iteration).

Incorrect links (unhealthy dependency)

The unhealthy dependencies are indicated with a red coloured line, when the successor is planned in the previous timebox (Program Increment or Iteration).

None

Dependencies are not displayed.

All

All dependencies are displayed.

Soft links are just and information about a dependency between to tasks and have no scheduling impact.

Soft-links can be created using drag and drop or by clicking on the link ring which appears on the right edge of the card when you hover over the card with the mouse pointer.

There are four standard types of dependencies which are called 'strong' link which have a scheduling impact.

When in auto scheduling mode such links will adjust the linked task's dates:

  • End to Start
  • End to End
  • Start to End
  • Start to Start

Strong links are displayed as a dashed lines and you can use them to indicate when a task should begin or end in relation to other tasks.

Strong-links can be only created by clicking on the link rings which appears on the right edge of the card when you hover over the card with the mouse pointer.

Such links can be visualised also using the Gantt module. To learn more about strong links go to Task dependencies - Link types.