Content
 BigPicture

About BigPicture

BigPicture installation

Quick start with BigPicture

BigPicture Export

Tutorials and tips

Integrations

 BigPicture release notes

BigPicture Cloud Backlog

 BigGantt

About BigGantt

BigGantt - Important Notice

BigGantt installation

BigGantt Cloud Backlog

 BigGantt release notes

Shortcuts
 Release notes
 BigPicture
 Jira Cloud

 Jira Server

 Trello

 BigGantt
 Jira Cloud

 Jira Server

 BigTemplate
 Jira Cloud

 Jira Server

 BigPicture Enterprise
 Jira Cloud

 Jira Server

Knowledge Base

Tutorials and tips

Search


The synchronization of the following field types is supported:

      • Date picker
      • Date time Picker
      • Original estimate (Time tracking field)

Date time picker fields are only available on Jira server versions.

It is also possible to disable the synchronization with Jira by selecting the --Not Synchronized-- option. By default the Start / End date custom fields created during the installation are selected.

Date pickers as Start and End dates

Date picker with Original Estimate

The video below shows what happens with your task when Original estimate of Time tracking is used as the End date. As the Original estimate is mapped as the End date, moving the right edge of the tasks changes the OE only. When the right edge is moved both the Start date and Original estimate are updated.

As the Remaining estimate is set, changing the Original estimate affects the progress calculation: