Search

Categories
 BigPicture

About BigPicture

BigPicture installation and updates

Quick start with BigPicture

BigPicture Sizing Guide

Cloud vs. Server - Key Differences in BigPicture on These Platforms

BigPicture Export

Progress Tracking

Tutorials and tips

Integrations

 BigPicture 7.10 and earlier

Concept of a Program

Setting up BigGantt and BigPicture to support next-gen projects


 BigPicture release notes

BigPicture Cloud Backlog

 BigGantt

About BigGantt

BigGantt installation and updates

Cloud vs. Server - Key Differences in BigPicture on These Platforms

 BigGantt release notes

Shortcuts
 Release notes
 BigPicture
 Jira Cloud

 Jira Server

 Trello

 BigPicture Enterprise
 Jira Cloud

 Jira Server

 BigGantt
 Jira Cloud

 Jira Server

 BigTemplate
 Jira Cloud

 Jira Server

Knowledge Base

Tutorials and tips

Trust Center


Quick overview of Effort Modes:

Effort ModeHow is the allocation being calculated?Additional notes
Original EstimateBased on Original Estimate - evenly distributed over Task's duration taking into account Resource's non working days.Task have no Original Estimate - the warning is returned.
Remaining Estimate

a) Work has not been logged:

Start date until yesterday - The allocation on the past days is displayed as '0'

Current date (today) to End date - The allocation for the remaining duration is displayed as Remaining Estimate evenly distributed over remaining duration.

b) Work has been logged:

Past duration (start date until yesterday) - the allocation is displayed as Logged Work (Time spent) evenly distributed over the past duration of the task.

Remaining duration (current date (today) to end date ) - the Remaining estimate is evenly distributed over the remaining duration.

1) If the Task's Remaining estimate value is not set (--) then Original Estimate is used when available.

2) If the Task is scheduled entirely in the future (Start date > = today) then only Remaining Estimate is shown (evenly distributed over Task's duration)

2.1) If there is no Logged Work the warning is returned.

3) Task is entirely in the past (today > end date) only Logged Work is shown.

Story PointsBased on Story Points - evenly distributed over Task's duration taking into account Resource's non working days.

If the Task has no Story Points the warning is returned.

When the "Show overall assignment" (Enterprise feature) is enabled the capacities may be misleading. This is due to the planning process using the Board module and the fact that Story points should not be converted to time units.