Content
 BigPicture

About BigPicture

BigPicture installation

Quick start with BigPicture

BigPicture Export

Tutorials and tips

Integrations

 BigPicture release notes

BigPicture Cloud Backlog

 BigGantt

About BigGantt

BigGantt - Important Notice

BigGantt installation

BigGantt Cloud Backlog

 BigGantt release notes

Shortcuts
 Release notes
 BigPicture
 Jira Cloud

 Jira Server

 Trello

 BigGantt
 Jira Cloud

 Jira Server

 BigTemplate
 Jira Cloud

 Jira Server

 BigPicture Enterprise
 Jira Cloud

 Jira Server

Knowledge Base

Tutorials and tips

Search


Original Estimate Mode

This is the default effort mode in which the Original estimate is evenly distributed over the task's duration, taking into account Resource's non working days. The non working days can result from Workload plans, Holiday Plans or the Working schedule. 

Original estimate is a 'Time tracking' field so to add it to your issue screen add the 'Time tracking'.


The video below show an example of the calculation using a task with 1w (40h) Original estimate. Please note that in this example date picker type of fields are used to determine the start and end position of the task. Also, using drag and drop a different resource - Calvin - is assigned to the task. Calvin is available for only 3d in this particular week hence the tasks duration is adjusted. Another thing worth mentioning is that Angela will not appear on the Resource list as she is not assigned to any tasks in the specified period.

Warnings 

If the Task does not have Original Estimate then the warning shows up (a red line that contours the Task) - considering 'Show warnings' feature is enabled