Content
 BigPicture

About BigPicture

BigPicture installation and updates

Quick start with BigPicture

BigPicture Sizing Guide

Cloud vs. Server - Key Differences in BigPicture on These Platforms

BigPicture Export

Progress Tracking

Tutorials and tips

Integrations

 BigPicture release notes

BigPicture Cloud Backlog

 BigGantt

About BigGantt

BigGantt - Important Notice

BigGantt installation and updates

BigGantt Cloud Backlog

Cloud vs. Server - Key Differences in BigPicture on These Platforms

 BigGantt release notes

Shortcuts
 Release notes
 BigPicture
 Jira Cloud

 Jira Server

 Trello

 BigGantt
 Jira Cloud

 Jira Server

 BigTemplate
 Jira Cloud

 Jira Server

 BigPicture Enterprise
 Jira Cloud

 Jira Server

Knowledge Base

Tutorials and tips

Search

Remaining estimate mode

In this mode the Remaining estimate and Logged work are evenly distributed over the task's duration, taking into account Resource's non working days. The non working, marked as grey, days can result from Workload, Holiday  or Absence Plans.

The Remaining estimate, if available, will be evenly distributed starting from today and onward, the logged work will be evenly distributed starting from yesterday and going backward.

If the Remaining estimate is not available, the Original estimate of Time Tracking will be used.

Warnings 

If the Task does not have Remaining Estimate then the warning shows up (a red line that contours the Task) - considering 'Show warnings' feature is enabled