Resources non-working days
The capacity of your resource is derived from the Workload plans and then further reduced by non-working days resulting from Holiday plans and Absence plans.
The details algorithm explaining the non-working day definition is shown below:
The formula for calculating the capacity of an Individual Resource:
- individual_capacity_day =
a. workload_day * individual_efficiency_day, if it's a working day
b. 0, if it's non-working day