Content
 BigPicture

About BigPicture

BigPicture installation and updates

Quick start with BigPicture

BigPicture Sizing Guide

Cloud vs. Server - Key Differences in BigPicture on These Platforms

BigPicture Export

Progress Tracking

Tutorials and tips

Integrations

 BigPicture release notes

BigPicture Cloud Backlog

 BigGantt

About BigGantt

BigGantt - Important Notice

BigGantt installation and updates

BigGantt Cloud Backlog

Cloud vs. Server - Key Differences in BigPicture on These Platforms

 BigGantt release notes

Shortcuts
 Release notes
 BigPicture
 Jira Cloud

 Jira Server

 Trello

 BigGantt
 Jira Cloud

 Jira Server

 BigTemplate
 Jira Cloud

 Jira Server

 BigPicture Enterprise
 Jira Cloud

 Jira Server

Knowledge Base

Tutorials and tips

Search


Lag Time

Lag time is the time period calculated in days dividing the tasks linked. The tasks are recalculated according to their types when their current position indicates time gap greater or shorter than the Lag time set for that particular link.

If the value is a positive number the tasks will be separated by the given number of days. If on the other hand the Lag time is a negative value than the tasks will 'overlap'.

The working and non-working days are both included in the lag time calculation. Parent tasks can start / finish on the non-working days when a lag time is applied: