Search

Categories
 BigPicture

About BigPicture

BigPicture installation and updates

Quick start with BigPicture

BigPicture Sizing Guide

Cloud vs. Server - Key Differences in BigPicture on These Platforms

BigPicture Export

Progress Tracking

Tutorials and tips

Integrations

 BigPicture 7.10 and earlier

Concept of a Program

Setting up BigGantt and BigPicture to support next-gen projects


 BigPicture release notes

BigPicture Cloud Backlog

 BigGantt

About BigGantt

BigGantt installation and updates

Cloud vs. Server - Key Differences in BigPicture on These Platforms

 BigGantt release notes

Shortcuts
 Release notes
 BigPicture
 Jira Cloud

 Jira Server

 Trello

 BigPicture Enterprise
 Jira Cloud

 Jira Server

 BigGantt
 Jira Cloud

 Jira Server

 BigTemplate
 Jira Cloud

 Jira Server

Knowledge Base

Tutorials and tips

Trust Center

Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Div
classpage-wrapper


The work progress can be displayed in form of a status based progress (eg. numer of issues in statuses other than Resolved / numer of issues in Resolved status group) using different units:

  • Story Points
    Image Removed
  • Tasks
    Image Removed
  • Time spent
Image Removed

The capacity allocation (planned vs capacity) can be displayed in form of a progress bar using different units:

  • Original estimate
    Image Removed
  • Remaining estimate
    Image Removed
  • Story points
Div
classpage-content


Image RemovedImage Added

Working with Totals

Totals will will help you in, both, planning and monitoring the execution of your Time-boxes.

There are different indicators or aggregations which can be displayed for each of the Time-boxes as well as at the Team level:

Info

Once enabled, Totals boxs boxes will be displayed only if data is available in a particular box (Team Tasks assigned with estimates)

Feature

Image Added

DescriptionWork progressCapacity allocation
Info

'Totals' indicators displayed at Team and unassigned level will include data relevant to a selected team or Team unassigned row.


Totals typeAggregate byFormulaScreenshot
Work progress

Story Points (SPs)

Sum SPs of Done status category tasks / Sum SPs of all tasks in Box scope

Image Added

Tasks

Count "Done" status category tasks / Count all tasks in Box scope

Image Added

Time spent (TS)

Sum Time Spent of all tasks in Box scope /
Sum (Time Spent + Remaining Estimate) of all tasks in Box scope

Image Added

Capacity allocation

Original estimate

Sum OE of all tasks / Box capacity in SPs

Image Added

Remaining estimate (RE)

Sum RE of all tasks/ Total Box capacity

Image Added

Story points

Sum SPs of all tasks / Box capacity in SPs

Image Modified


Overallocation warnings

If the allocation exceed the capacity a warning will be diasplayed displayed and progress bar will indicate the overallocation using a red colour.

–––––––––––––––

Go back to the Old Board - Interface overview.